910.04.02.05
“Test results shall be provided for relaxation testing of prestressing steel bars for the same heat number as the material supplied for the work”
- Does it also apply to strand?
910.05.02.01
“The diameter of a duct, or an equivalent diameter of a non-circular duct, shall not exceed 40% of the least gross concrete section thickness at the location of the duct.”
- This requirement is a structure design requirement, not a PT system requirement
910.05.03.01
“The pre-packaged dry grout mixtures shall be used within 6 months of packaging and shall be stored on site for a maximum of 1 month”
- duration on site should be increased to 6 months, with proper storage conditions
910.06.02 Grouting equipment
Read more
910.07.01
“Personnel employed or licensed by the manufacturer of the post-tensioning system shall carry out the work”
- we recommend an external certificate such as PTI level 1 as minimum
910.07.05.01
“For anchorages and couplers, samples shall be selected by the Contract Administrator on a random basis.”
- very unspecific. How many? Sizes? For what purpose?
View the comments this notice received through the registry. You can either download them all or search and sort below.
Some comments will not be posted online. Learn more about the comment status and our comment and privacy policies.
Download comments
910.07.04.01 “Fusion welding…
Comment on
OPSS 910 Construction Specification for Stressing Systems for Post-Tensioning
Comment ID
304
Commenting on behalf of
Comment status
Related actions
910.04.02.05 “Test results…
Comment on
OPSS 910 Construction Specification for Stressing Systems for Post-Tensioning
Comment ID
305
Commenting on behalf of
Comment status
Related actions
910.05.01.02 “Primary tendon…
Comment on
OPSS 910 Construction Specification for Stressing Systems for Post-Tensioning
Comment ID
306
Commenting on behalf of
Comment status
Related actions
910.05.02.01 “The diameter…
Comment on
OPSS 910 Construction Specification for Stressing Systems for Post-Tensioning
Comment ID
307
Commenting on behalf of
Comment status
Related actions
910.05.02.02 “Corrugated…
Comment on
OPSS 910 Construction Specification for Stressing Systems for Post-Tensioning
Comment ID
308
Commenting on behalf of
Comment status
Related actions
910.05.03.01 “The pre…
Comment on
OPSS 910 Construction Specification for Stressing Systems for Post-Tensioning
Comment ID
309
Commenting on behalf of
Comment status
Related actions
910.07.01 “Personnel…
Comment on
OPSS 910 Construction Specification for Stressing Systems for Post-Tensioning
Comment ID
310
Commenting on behalf of
Comment status
Related actions
910.07.05.01 “For anchorages…
Comment on
OPSS 910 Construction Specification for Stressing Systems for Post-Tensioning
Comment ID
311
Commenting on behalf of
Comment status
Related actions