This consultation was open from:
November 24, 2022
to December 15, 2022
Decision summary
Decision is to move forward with publishing process.
Decision details
Decision is to move forward with publishing SSP 104S06 in CPS and MTO Technical Publications Portal.
Effects of consultation
The posting received six comments that were addressed by the revisions in Table 1 - Pipe Condition Codes.
Supporting materials
Connect with us
Original proposal
Proposal details
The Special Provision supplement the changes made to OPSS PROV 410 Construction Specification for Pipe Sewer Installation in Open Cut and OPSS PROV 421 Construction Specification for Pipe Culvert Installation in Open Cut. The proposed changes include the basis of payment for post installation inspections invoked during construction.
Supporting materials
Comment
Commenting is now closed.
This consultation was open from November 24, 2022
to December 15, 2022
Comments received
Through the portal
1