2.6.1 Drawing Numbers It…

TCP number

000-0184

Comment ID

393

Commenting on behalf of

Individual

Comment status

Comment approved More about comment statuses

Comment

2.6.1 Drawing Numbers

It says what to do if the drawings are preliminary (P1), and it says what to do if the drawings are rehabs (R2-1). But, when I look at the structural sheets of new bridges they are commonly prefixed with "S" (e.g., S1). Should the manual not say that more clearly? Or is the intent to actually drop the "S" for the structural sheets?