This consultation was open from:
March 18, 2025
to April 15, 2025
Decision summary
No comments were received. The ministry will proceed with the publication of the Special Provision as posted in Technical Consultation Portal in the Technical Publications site.
Decision details
Implementation of the Special Provision
Supporting materials
Connect with us
Original proposal
Proposal details
MTO is proposing administrative changes to modify “shall” to “will” for Owner-led actions
For the Fuel Price Adjustment calculation (GC 8.02.04.02.06):
-
MTO is changing advertising and advertised for tender to “month prior to tender opening” to clarify intent of MTO’s current practice
-
MTO is adding to c) that it is the total “estimated” monthly fuel consumption
Table 8.02.04.02-1 of the MTO GCs is being amendment to include new fuel consumption rates as follows:
-
Recycled Asphalt Pavement (RAP) at 0.21 l/m2
-
Hot-In-Place-Recycling (HIR) at 0.32 l/m2
-
Caisson and Continuous Flight (CFA) – Earth at 12.2 l/m2 with an associated formula as explained in Note 11 in Table 8.02.04.02-1
-
Caisson and Continuous Flight Auger (CFA) Piles – Piles at 36.6 l/m2 with an associated formula as explained in Note 11 in Table 8.02.04.02-1
Supporting materials
Comment
Commenting is now closed.
This consultation was open from March 18, 2025
to April 15, 2025
Comments received
Through the portal
0