Proposal summary
Revision to OPSS 517 published in November 2023 and SSP 517F01 now includes the requirements for installation and removal of a Temporary Flow Passage System. These revisions required a revised Construction Administration and Inspection Specification (CAIS) 517.
Proposal details
The revision to OPSS 517 and SSP 517F01 requires a revision to CAIS 517.