Commentaires

Consulter les commentaires qu'a reçus cet avis par l'entremise du registre. Vous pouvez soit tous les télécharger, soit utiliser la fonction de recherche et de tri ci-dessous.

Certains commentaires ne seront pas affichés en ligne. Apprenez-en davantage sur l'état du commentaire et sur nos politiques relatives aux commentaires et à la protection de la vie privée.

Télécharger les commentaires

Search comments

Comment ID

563

Commenting on behalf of

Individual

Comment status

Comment approved More about comment statuses
Section 2.1.1.2 Qualifications Required for Inspections of MTO Structures Regarding Lead Inspectors: 1) Will MTO Bridge Inspection Workshops be offered on an annual basis, to ensure there are adequate opportunities for assistant inspectors to qualify as lead inspectors? Read more

Comment ID

564

Commenting on behalf of

TSI Inc.

Comment status

Comment approved More about comment statuses
Hi, Subject: Clarification on Extent of Inspection for SBGR under OSIM I would appreciate your guidance regarding the extent of inspection required to meet the legal requirements under the Ontario Structure Inspection Manual (OSIM). Read more

Comment ID

566

Commenting on behalf of

Individual

Comment status

Comment approved More about comment statuses
1) Based on the Concrete - Substructures and Superstructures Defect Definitions Table 2.5.4.1. How is an inspector to know if concrete has been cured at temperatures above 70 degrees Celsius resulting in DEF based on a visual observation? Read more

Comment ID

568

Commenting on behalf of

Individual

Comment status

Comment approved More about comment statuses
For Section 2.1.1.2. in reference to the number (i.e. 100 or 20) previous OSIM Inspections required for the lead inspectors, should the total not be specific to the type of structure being inspected? I.e. Read more

Comment ID

569

Commenting on behalf of

Individual

Comment status

Comment approved More about comment statuses
Subject: Comment on 2026 OSIM Draft Review – Section 2.1.2 Qualifications Required for Inspections of MTO Structures I am writing to provide feedback on the proposed inspector qualification requirements outlined in the 2026 OSIM draft. Read more

Comment ID

572

Commenting on behalf of

City of Ottawa - Asset Management

Comment status

Comment approved More about comment statuses
A 2009 MTO Memorandum provides clarification on OSIM inspection timing requirements for newly constructed and rehabilitated structures, indicating that the first inspection is to be completed within two calendar years of construction contract completion and opening of the structure to traffic. Read more

Comment ID

573

Commenting on behalf of

City of Ottawa - Asset Management

Comment status

Comment approved More about comment statuses
The requirement to record defect quantities in whole numbers for square metres (area) and linear metres (length) is generally appropriate for larger structures or elements and has minimal impact on the overall structure condition rating or BCI. Read more