Comment
1355.04.02.05 Notification of Placement
Plant schedules are still being adjusted 14 days in advance. Schedules should be submitted no earlier than 7 days ahead. Day-to-day changes should not require written notification to the CA. This is between the precaster and the contractor. The CA receives notification when each production lot is complete.
Submitted October 24, 2025 2:54 PM
Comment on
New specification - OPSS 1355 – Precast Concrete – Materials and Production
TCP number
000-0263
Comment ID
496
Commenting on behalf of
Comment status