⦁ MTOD 988.101 - Note 4 and Note A should be combined, otherwise Note A contradicts Note 4.
⦁ MTOD 994.110 - It seems as though additional labelling should be provided (such as leaders pointing to the post in both the Elevation and Profile views to identify the post). Also, rebars are identified in the Plan view but there is no indication as to the length of the rebar or where within the length of the post the rebar is located. Is the Ecoposte a proprietary product?
⦁ For the SBGR connections to parapet walls, there is no indication or acknowledgement of the use of curb and gutter on the approaches; is it intended that curb and gutter NOT be used on the approaches? If so, how is erosion of the rounding/shoulder granular to be prevented?