Energy Attenuator, End Terminal, Steel Beam Energy Attenuating Terminal (SBEAT), Next Generation Terminal (NGT) System

TCP number
000-0207
Notice type
Standard
Applies to
MTOD - Ministry of Transportation Drawing
No. specification
MTOD 922.190 (new) and SSP 732S03 (update)
Posted by
Highway Design Office
Notice stage
Decision
Decision posted
Comment period
June 21, 2024 - July 19, 2024 (28 days) Closed
Last updated

This consultation was open from:
June 21, 2024
to July 19, 2024

Decision summary

The NGT terminal system, a steel beam energy attenuator (SBEAT) system, is a good addition to the list of
contractor option systems.

Decision details

The NGT Terminal is a Steel Beam Guide Rail (SBGR) terminal system that was successfully crash tested
to meet the AASHTO Manual for Assessing Safety Hardware (MASH) Test Level 3 (TL-3). The NGT
Terminal is proposed for implementation as a Steel Beam Energy Attenuating Terminal (SBEAT) for use on
highway construction projects.

Comments received

Effects of consultation

No comments were received.

Supporting materials

Connect with us

Sign up for notifications

We will send you email notifications with any updates related to this consultation. You can change your notification preferences anytime by visiting settings in your profile page.

Follow this notice

Original proposal

TCP number
000-0207
Type notice
Standard
Posted by
Highway Design Office
Proposal posted

Comment period

June 21, 2024 - July 19, 2024 (28 days)

Proposal details

This is part of the ministry’s ongoing efforts to implement roadside safety hardware products that meet crash
test requirements of the AASHTO Manual for Assessing Safety Hardware.

Supporting materials

Comment

Commenting is now closed.

This consultation was open from June 21, 2024
to July 19, 2024

Connect with us